We apologize for the short-notice given to residents for the need to cancel our planned AGM. Planned round a presentation about developments on ‘The Cameron Toll Re-development’, C.B.R.E. requested a move to an unconfirmed later date.
(a) As a result of these changes C.B.R.E. will now hold an ‘in-store’ presentation on the 19th November; next to the Gym stairs – between 16:00 and 19:00 and it is strongly recommended that residents attend where possible.
(b) The Scottish Power Network (SPEN) work progresses through the area and this will necessitate traffic flows under Lights Control which will inevitably lead to delays to journeys – so please make allowances for planned workings:
Kilgraston Road will be closed for approximately 5 weeks and therefore there will no direct through route from Marchmont to West Mains and vice-versa.
Work on Mayfield Road – from Relugas Road up to Lygon Road – will be continuous with an estimated finish in the last week of November.
There will be a period of ‘no working’ between December 2026 and January 2027.
Starting in February, the work temporarily halted at Lygon Road, will recommence across Mayfield Road and continue down and into Blackbarony Road continuing into Gordon Terrace.
It is the intention of your Conservation Committee to reset the AGM to a suitable date in January and there will opportunities to follow through on the November C.B.R.E. presentation.
If you’d like to join the list to receive our free newsletter, please subscribe below.